Community Partners

Deh Gah Got'ie First Nation

Fort Providence Métis Council

Hamlet of Fort Providence

Project Management

Associated Engineering

Prime Contractor

Ruskin Construction Ltd.

Design Engineer

Infinity Engineering Group

Quality Assurance

Levelton Consultants Ltd.

Sargent & Associates

EBA (a Tetra Tech Company)

Territorial Advisors

BPTEC-DNW Engineering Ltd.

T.Y. Lin International

  

Nov. 30, 2012

The bridge is open! Visit the photos page for pictures from the official opening events.

September 11


Thank you to Kelly O'Connor for this great shot of the North approach paving work.

August 23

Bridge deck work continues, with all deck panels now placed and panel grouting complete. Reinforcing steel for the deck panel infills is complete, and 50% complete for the curbwork. Interior formwork is near completion, and exterior formwork is more than 50% complete. Curb concrete is one third poured, and concrete infills is one half complete.

Lock Up Devices (LUDs) are connected to the Pier 2 North pier head in preparation for truss connection. The asphalt plant has been mobilized and is being set up in preparation for paving.

It is expected the Bridge will be open for traffic in November.

August 14

Thank you to Phil Goulet for his picture from the early days of the Deh Cho Bridge construction. Phil will receive a Department of Transportation water bottle and be entered into a draw for a laptop bag.

August 13, 2012

All of the deck panels are now in place, and the rebar and panel grouting for the deck panels are nearing completion. Work has started on the curb concrete, curb formwork, and concrete infills. Interior and exterior formwork is more than 50% complete. The placement of the membrane for the driving surface is expected to begin later this month, after which paving will commence.

August 3, 2012

All deck panels have now arrived on site, with 262 of the 278 deck panels installed. Grouting is complete on 211 of the panels, and rebar infills have been completed on 189 of the panels. The ceiling slab for the abutment utility room has been casted, as has the north approach slab. South approach earthworks work continues.

July 24, 2012

Earthworks continues on the south approach. The north approach around the abutment has been filled in, and GeoFoam has been placed above the north abutment, work continues preparing to place concrete for the approach slab (formwork and rebar ongoing). A total of 192 deck panels have been placed (over 2/3 complete).

Concrete infills have been placed between the precast deck panels from the north abutment up to panel #55 (above P2N). Grout has been placed under 167 panels. Curb forms and strike plate are being installed on the north end of the bridge. The south abutment wing walls have been poured and the formwork stripped, and prep for the mechanical room roof is ongoing. The weigh in motion cameras and wiring have been installed.

July 8, 2012


Photo taken July 8, 2012 by Ron Bonnetrouge. Ron will receive a DOT aluminum water bottle and his name will be entered into a draw for a DOT laptop bag.

June 22, 2012

Earthworks continues on the south approach. Deck panels continue to be delivered to the south side, waiting for installation, with work bridge components being sent out. 97 deck panels have been placed on the north truss, and 110 have been stored on the south side. 56 deck panels have now been grouted. Transverse jacking blocks have been installed at piers 1-3 south, and bearing bolts have been completed at piers 1-2 south. Delivery of sand and aggregate for concrete is completed.

June 13, 2012

Earthworks are progressing with work on the south approach. Crews are stockpiling dressing rock for the south abutments.

Thanks to Mary Savas for her picture (above) of the Deh Cho Bridge construction from her May 2012 trip. Mary will receive a DOT aluminum water bottle and will be entered into a draw for a laptop bag.

June 7:

Installation of the deck panel interior formwork for the north deck panels is complete. Installation of the exterior forming support system has begin. Grouting of deck panels continues. Deck panel exterior form soffits are being installed.

June 4, 2012

Grouting for the deck panels continues. Cabling for the south pylon is now complete. Technical problems on the south web cam have now been resolved and both south and north images are now functioning.

June 1, 2012

With good weather, work continues on a number of fronts. Deck panel installation is continuing at a steady pace, with 85 panels installed on the north side and steady progress on the south. Formwork for the deck panels is being installed. Cabling for the south pylon continues with forestay cables to pier 4 south installed. Equipment is mobilizing for the completion of work on the abutments.

May 29, 2012

Northwestel crews have completed the installation of a fibre optic cable crossing the Mackenzie River on the Deh Cho Bridge. This has allowed Northwestel to deliver more Internet broadband to North Slave communities, with fibre connectivity complete from Edmonton to Yellowknife. Previously, telecommunications traffic crossed the Mackenzie River by microwave. For more information, please click here.

May 22, 2012

Do you have a picture of the Deh Cho Bridge since both sides were joined that you want to share? Send it to commcoordinator@gov.nt.ca. If we use it on the website, we’ll send you a cool prize, and enter you into a draw for a Department of Transportation laptop bag.

All north side deck panels are now installed. Rebar is being placed in the deck panel joints.

May 3, 2012

Work continues on the south pylon and cables. In the coming week, the crown of the south pylon will be welded, and prep work will begin on the first set of forestay cables. Infill rebar is being installed between already-installed deck panels, while additional deck panels continue to be delivered and installed.

April 27, 2012

Construction continues, with both sides of the bridge now connected and deck panels being laid. The second A-pylon and cables are being installed. The bridge is now more than 90% completed, with the critical warm weather phase of construction soon to begin.